Department of Orzology Y2K Plan
Last updated: March 31, 1999 Customized Applications Project lead: I.S. Manager Debra Brantz Date of completion of inventory of applications: March 20 Date of completion of spreadsheet to track progress on applications: March 23. Document name is: trakxmpl.xls All costs and timelines are being estimated and tracked on an application-by-application basis. Funding is available from current departmental sources.
Research Equipment Date of completion of inventory of research equipment: estimated to be May 21 Date of completion of assessment of research equipment: estimated to be June 15. Date of completion of contacts with manufacturers: estimated to be June 30. Date of completion of decisions to fix, replace, or discard, for all equipment: estimated to be July 31. All costs and timelines are being estimated and tracked on an item by item basis. Total costs and funding sources have not been identified.
Computers Project leader: a project leader was assigned for each group of computers. Project leaders are expected to share information. Target dates:
Hardware: This is an issue only for PCs. To be corrected by June 30, except for older equipment where this is not cost-justified. Operating systems: Target date for fixing is also June 30. Three Windows 3.1 computers cannot be made fully Y2K compliant at the OS level; a decision will be made by the end of September whether to replace these (it is not cost-effective to upgrade them). Data (databases, spreadsheets, data transfer): Work on data (spreadsheets, etc.) will largely be delegated to faculty and staff employees. Training sessions have been scheduled for 4/15, 4/25, and 5/1, for the entire department.
Building Alarm and Access Control Systems: Funding for central system upgrades: Discussions have been held with the Dean of the Division of Boolean Logic, and a budget augmentation request has been submitted. Decentralized systems: The department has no standalone alarm or access systems.
Networking Equipment Date departmental networking equipment assessment was completed: March 29. All costs and timelines are being estimated and tracked on an item by item basis. Only one item has been identied as a problem; it needs a software upgrade, which is available at no cost.
Administrative Equipment: All costs and timelines are being estimated and tracked on an item by item basis. Total cost is minimal.
Leased Buildings Building liasion: The deputy Curator has been identified to Real Estate Services as the liaison for the department for this leased building.
Supplies and Services
Contact for questions and comments about this page: johnb@uclink4.berkeley.edu Web Administrator: salas@uclink4.berkeley.edu Last Updated Tuesday, 29-Feb-2000 11:53:16 PST Berkeley Campus Home page Copyright Regents of the University of California, 1999 Disclaimer: The University assumes no liability if the information on this page is used for other than University purposes. |